![]() |
![]() |
||||
![]() |
![]() |
||||
|
|||||
Forest of Dean slope stabilisation Low Impact Benefits Highway Embankment Stabilisation Railway Embankment Stabilisation
|
Low impact benefits of EKG slope stabilisation Project outline Repair of earthwork failures involving landslips represents significant expenditure for Highways England across the national network each year. A variety of engineering solutions conventionally used involve significant earthworks and import of new construction materials, resulting in the generation of waste and a high carbon footprint. The earthwork which supports the northbound A419 dual carriageway, just north of Swindon, on its approach to the A361 Highworth Road over-bridge, comprises a 6m high embankment of Oxford clay at an angle of 26° within which a 15m wide failure had developed from the crest of the slope to approximately 2.0m from the toe, thus undermining the vehicle restraint system over a length of 12m. Previous remediation with granular replacement had proved unsuccessful. The alternative to the EKG system under consideration comprised excavation and rebuild using the excavated material as fill for reinforced soil. This was not favoured owing to access restrictions and the impact of extensive earthworks using large plant and the associated level of traffic management that would have been required. Project implementation The design comprised:
The construction sequence comprised:
After the completion of the active treatment, the site was decommissioned immediately. Decommissioning summary:
Project outcomes The delivered benefits of the EKG system included:
Low impact construction: installed and connected electrodes and cables showing the DC power supply on a temporary concrete plinth; AC generator; fuel tank; security mast. On this site the installation of 46 driven and bored electrodes provided detailed information which confirmed the anticipated ground conditions. This in turn permitted redesign of the array and significant savings due to fewer installations, less cable and lower overall fuel consumption. As such the EKG system is adaptable and responsive to the observational method. |
||||
“Of all the remediation solution options for the embankment Electrokinetic’s provided the least disruptive and low impact solution that improved the embankment stability. Implementation and testing were carried out discretely with results as predicted. Works were co-ordinated and managed effectively.” Mike Reid, Operational Manager, Road Management Services (Gloucester) Limited
![]() Slope climbing rig. Tracking of the machine up and down the slope was sufficient to smooth out slight undulations in ground surface. |
|||||
|
|||||
|
|||||
![]() |
Home | EKG Dewatering | EKG Slope Stabilisation | EKG Technology | EKG News | Case Studies | Downloads | Contact | Sitemap | ||||
Electrokinetic is a trading name of Central Alliance Pre Construction Services Limited, Alliance House, Junction 41 Business Park, South Park Way, Wakefield, WF2 0XJ
|